2004 REGIONAL TRANSPORTATION PLAN
UPDATE
The Shasta County Regional Transportation Planning Agency is
starting the process for updating the Regional Transportation Plan (RTP) in
December of this year. The update cycle for the RTP is every three years. This
update must be completed by September 1 2004. To accomplish the update of the plan and complete financial and
project analysis, the target for completing the administrative draft 2001 RTP
is June 1, 2004.
A detailed plan is needed primarily to ensure that the
document is comprehensive and that all Stakeholder, Public and Private sectors
inputs are accurately represented.
Additionally, A state RTPA Task Force has made significant
recommendations to the California Transportation Commission that strive to
improve the consistency of all RTP statewide documents. The recommendations made by that group need
to be accounted for in this update.
The 2001 RTP was a major undertaking for the regions
resources. At that time, resources were
available to conduct significant planning efforts whose deliverables/byproducts
were used to update the document. The
below listed planning efforts will streamline the production of this
update. Examples of these efforts
include the following:
1 The Shasta County Travel Demand Model
was updated concurrent with the update of the 2001 RTP. The model update process included
socioeconomic data to prepare estimates and projections for Shasta County. The Model output was used for the regional
plan for inputs in the prioritization process.
The completed model was one of the tools used to validate needs and
project selection. The model could be
used in the 2004 cycle to rank projects but due to the lack of funding
availability in the STIP a level of effort is not warranted. The decision to
develop a process to re-rank projects using the model will be made early in the
process by the working group.
2. A Street Master Plan for the City of
Redding was prepared.
3. The Redding Area Bus Authority
conducted a short and long-range transit study for the RABA service area. This plan is designed to identify both
operating and capital needs for a 10-year short range and 25-year long-range
plan horizon.
4. Each of the cities and the county were
sub-allocated the funding from the Transportation Enhancement exchange. The RTPA required each of the recipient
agencies to conduct a public meeting to gather ideas for expenditure of these
funds. The results of this process
could be used to identify additional non-motorized needs.
5. Although the RTPA staff developed
procedures for a Congestion Mitigation Air Quality (CMAQ) program in Shasta
County the region continued to gain attainment. Shasta County was not designated as a nonattainment area for ozone. CMAQ funding will become available for
projects that reduce traffic congestion and air pollution from mobile sources
when, or if, the region is designated nonattainment. These projects will need to be included in the RTP.
6. The RTPA continues to participate in
the California Oregon Advance Transportation (COATS) project that is studying
applications for intelligent transportation systems in rural areas. ITS projects will continue to be integrated
in the updated RTP.
A 2004 Regional Transportation Plan Working Group will be
formed to assist in developing the plan. The membership will be similar to the
2001 group. This is a requirement of
the process in order to engage all stakeholders. The working group will be asked to participate in the development
of the plan. This will require a
commitment of resources by the agencies.
A schedule of meetings will be provided for review to the TAC/Working
Group during the kickoff meeting in January 2004.
Consistent with the prior period efforts, this update of the
plan considers an unconstrained transportation needs analysis. The goal of using an unconstrained approach
is to develop prioritized lists of needed projects that can then be drawn from
for programming as funding becomes available.
This update will need to be a multimodal approach focusing on streets,
roads and highways; transit; nonmotorized; goods movement; passenger rail; and
airports.
The goals and objectives, both short and long range, of the
RTP need to be critically reviewed and reaffirmed or amended by the
stakeholders. It is extremely important
to make sure we agree on our vision for Shasta County=s transportation system.
A broad based effort will be required by the cities of
Anderson, Redding and Shasta Lake; Shasta County; Caltrans; and other
stakeholders to identify transportation needs, associated projects and purpose
for the region. The needs should be
quantified where possible and attached to a geographic location in the
county. The projects that address the
needs are to be described in sufficient detail in order to analyze with the
travel demand model and subsequent air quality modeling, if needed. An estimated total project cost including
support costs expressed in year 2004 dollars needs to be assigned to each
project. The year when the project or
distinct phase of the project will be operational is also needed. All project lists in the current RTP need to
be updated.
While the stakeholders are identifying needs and projects,
the RTPA staff will be reviewing and documenting the current state of
transportation. Population and land use
build- out projections developed for the updated travel demand model will be
used in the RTP. The California
Transportation Plan, and other local plans will be reviewed to ensure
consistency between the developing RTP and these plans. Three funding alternatives are proposed:
one, a reduced funding, two, continued current rate of funding, and three a
high level across the board increase.
After the broad based unconstrained needs assessment is
updated and the project lists are reviewed, the RTPA staff in consultation with
the Working Group, could utilize the travel demand model to validate needs and
project selection. The level of effort,
at this step, will be tempered by the lack of short term funding
available. The projects will be arrayed
by delivery year by staff. The working
group and staff will then compare the list to the goals and objectives of the
plan. Priorities will be assigned based
on a process that the project sponsors and working group agrees upon. Other factors consistent with the goals and
objectives of the plan will also be used.
Finally the three alternative funding alternatives will be applied to
the list and a fundable list developed.
An unconstrained list will also be made with the projects that fall outside
of the fundable list.
The following are the tasks and schedule needed to complete
the update:
1. December - Initiate the update process
with the Agency approval of the direction set in this document. The Technical Advisory Committee members
have discussed the update plan and reviewed the prospective working group
members listing. The RTPA staff have
presented a detailed work plan with a schedule of Working Group meetings for
comments. All short and long range
goals and objectives of the RTP need to be reviewed and updated. Public Notices
will be generated for each meeting date.
2. December 2004- Working Group kickoff
meeting to consider process of updating and editing the written goals and
objectives for the RTP. Work effort
will include updating exhibits and identifying transportation needs for the
next 20 years based on the General Plans of the cities and county and the State
Transportation Plan.
3. January, 2004 – Working group meetings
to discuss the Streets and Roads update, confirm goals and objectives both
short and long run. A progress report
with issues identified early that may hinder progress will be reported to the
agency. Work will center on determining
that the Streets and Roads Project list is accurate, complete, etc. Drafts will be circulated back to the
working group members by end of each month.
Discuss data gathering required for chapter rewrites and financial
section inputs.
4. March 2004 – Working group meeting on
Transit goals and objectives. Confirm
goals and objectives both short and long run.
Determine Project list accuracy, completeness, etc. Draft to be circulated back to working group
members by end of month. Discuss data
gathering required for chapter rewrite and financial section inputs.
5. April 2004 - Working group meeting to discuss Non-Motorized chapters. Additionally, a working group meeting to
update Goods Movements, Aviation, Rail, Land Use, Air Quality, and
Environmental Resources will be conducted.
Confirm goals and objectives both short and long run. Determine Project list accuracy,
completeness, etc. Draft to be
circulated back to working group members by end of month. Discuss data gathering required for chapter
rewrite and financial section inputs.
Presentation to Agency Members regarding revised and updated Project
lists for the Region from a Streets and Roads perspective.
6. May 2004 – Final Working Group meeting
to present administrative draft for consensus approval. Working group meeting will consider the
formulated plan alternatives impacts.
The alternatives will be two fold.
There will be financial alternatives and also alternatives based on mode
and environmental issues.
7. June 1, 2004 - Target date for 30 Day
public comment period start up.
Distribute copies to all stakeholders, working group members and others
as defined in the Public Involvement Guidelines standard practice.
8. July, 2004 – Review and react to all
comments, add or edit text. Prepare
Staff report for adoption, review with TAC committee and gain agreement of changes.
Hold Public workshop on the plan alternatives.
Take final comments from the public.
Gather comments on level of support needed in appendixes.
9. July 27, 2004 – Agency Meeting to
adopt the 2004 RTP and conformity findings.
10 August 2004 – Print and Distribute the
2004 RTP
11. September 1 – File Document with
Caltrans.
12. October 2004- Fall back date for adoption
of the RTP and conformity findings.